PERFORMANCE AUDIT OF THE CONSTRUTION OF THE
LOS ANGELES POLICE HEADQUARTERS FACILITY
~~~~~~~~~~~~~~~~~~~
EXECUTIVE SUMMARY
~~~~~~~~~~~~~~~~~~~
The Controller's Office has completed its performance audit of the construction of the
new Police Headquarters Facility. The primary objectives of the audit were to perform
an overall assessment of the management functions on the Police Headquarters Facility
project and to conduct contract compliance reviews of the two contracts with DMJM
Design / Roth+Sheppard Joint Venture, the project architect, and Vanir Construction
Management, Inc., the project construction management consultant.
BACKGROUND
On February 25, 2003 the Los Angeles City Council (City Council) approved a report
from the Municipal Facilities Committee, consisting of the Chief Administrative Officer,
Chief Legislative Analyst and the Office of the Mayor, for the construction of a new
Police Headquarters Facility on City-owned property. The need for a new facility to
replace the existing Parker Center building had been identified for a long time as it was
considered outdated, in need of expensive seismic retrofits and too small to
accommodate the present needs or projected growth of the Los Angeles Police
Department. The new Police Headquarters Facility is expected to bring much needed
facility improvements to support Los Angeles Police Department's mission to enhance
public safety.
The construction of the new Police Headquarters Facility is one of the most expensive
and visible projects the City of Los Angeles (City) has undertaken in recent years. To
date, the Police Headquarters Facility project has faced schedule delays and budget
increases due to land acquisition issues, construction cost escalation, local construction
market conditions, and changes to project scope. In June 2004, the Police
Headquarters Facility project was originally budgeted at $303 million with a scheduled
completion date of March 2009. Currently, the project is budgeted at $437 million with a
scheduled construction completion date of May 2009 for the Police Administration
Building and Main Street Parking / Motor Transport Division Facility, and June 2010 for
the Aiso Street Parking structure.
It is also worth noting that various aspects of the
project are also funded from the City General Fund and not reflected in the $437 million
dollar project budget. In 2007, $725 thousand was budgeted against the General Fund
for Fiber-optic and Copper communication connections to the Police Administration
Building. Additionally, there is a 2008 budget request for $16 million from the General
Fund for the purchase of freestanding furniture, radio systems, microwave systems,
MATV distribution system, audio/visual systems, voice and date network components
and computer servers.
The Department of Public Works Bureau of Engineering (BOE) is responsible for
delivering the Police Headquarters Facility according to directives from the Municipal
Facilities Committee. BOE is working in partnership with Los Angeles Police
Department and other City departments on project planning, development and design to
deliver a facility that meets the current and future needs of Los Angeles Police
Department.
As of December 2007 construction of the Police Administration Building was
approximately 47% complete with less than 2% change orders. Construction of the
Main Street Parking / Motor Transport Division Facility and Aiso Street Parking structure
parking facilities had not yet begun. Of the $437 million total project budget,
approximately $130 million had been expended.
SCOPE
The scope of this audit focused on the overall project management practices of the
Police Headquarters Facility project as performed by BOE. Two consultant contracts
were also included in the audit scope: Agreement No. 106467 with DMJM Design /
Roth+Sheppard Joint Venture and Agreement No. 109458 with Vanir Construction
Management, Inc. Contract No. C-110760 with Tutor-Saliba Corporation, the general
contractor on the Police Headquarters Facility project, was not included in our scope,
however we considered City project management practices related to the construction
contract.
BOE's construction administration process is largely governed by policies and
procedures found in BOE's Project Delivery Manual, which was reviewed and
referenced during the process review section of this audit.
The period covered by our audit is February 25, 2003 through December 31, 2007.
Fieldwork was performed between October 24, 2007 and February 1, 2008, which
included interviewing City personnel, consultants and contractors, and reviewing project
documentation and billing records.
The audit was conducted in accordance with Generally Accepted Governmental
Auditing Standards.
SUMMARY OF RESULTS
Overall, our audit disclosed that BOE's project management was adequate, including its
monitoring of construction activities. In addition, our audit disclosed that payments to
contractors were made in accordance with the contract terms.
Our audit, however, found that an alternative delivery strategy from the typical “designbid-build” method used may have been more advantageous, and resulted in lower
costs. In addition, we noted certain deficiencies in the negotiation process with the
construction contractor, construction management firm, and the architectural design
firm.
Due to the absence of clear BOE policies related to negotiating with a single bid
contractor and the minimal documentation maintained by BOE, it does not appear the
City achieved any substantial cost savings from Tutor-Saliba Corporation for the original
Police Administration Building construction contract of $231,337,246. In order to
achieve a true negotiation with Tutor-Saliba Corporation, BOE needed the authorization
from Municipal Facilities Committee to reject the bid and not award the contract.
Additionally, BOE did not utilize all available mechanisms in the cost negotiation
process with the project architect and the project construction management firm. As a
result, it is not clear whether BOE obtained the most favorable contract rates for these
two agreements, with a combined value of $26,500,000 (including executed
amendments).
KEY FINDINGS
SECTION I. PROJECT MANAGEMENT ASSESSMENT
There were limited cost savings on the single bid negotiations of the construction
contract.
The Police Headquarters Facility project received a single bid for construction of the
Police Headquarters Facility Police Administration Building, which was reduced
through discussions with the general contractor. Due to the nature of the fixed price
contract, absence of clear BOE policies related to negotiating with a single bid
contractor, and the minimal documentation maintained by BOE, it does not appear
that the City achieved any substantial cost savings from the general contractor
through negotiations. Rather, reductions were due to shifting costs to other
contractors or the City, substituting or eliminating some design elements, and
accelerating the payment schedule.
The City is not taking advantage of the Construction Manager at Risk delivery
methodology, which may have resulted in cost savings on the PHF project.
The Construction Manager at Risk method results in the engagement of the general
contractor at the design stage and has a guaranteed maximum price compensation
structure instead of a lump sum. BOE has not been permitted by City policy to add
Construction Manager at Risk to its available project delivery methodologies. As a
result, the City is limited in its ability to implement the most optimal method to deliver
its projects. The Construction Manager at Risk methodology is utilized by other
agencies and municipalities in California.
BOE does not have a formal plan to transition key employees off a project in the
event the employees leave City employment.
There appears to be one key individual, the former City program manager, now
retired, who holds the majority of historical knowledge related to the Police
Headquarters Facility project. By having critical project knowledge largely held by
one individual outside of City staff, the City risks having insufficient project
information if that individual leaves the project permanently or if a disagreement
should arise.
BOE does not have a fully effective contractor outreach program.
Several Los Angeles area general contractors, who were part of the BOE outreach
effort, were contacted to gain an understanding of why the contractors did not submit
a bid on the Police Administration Building. The common theme expressed by the
contractors was that they did not feel they knew about the Police Administration
Building early enough. As a result, they were busy with other projects when the
Police Administration Building was advertised. The contractors attributed this
problem largely to the City's lack of a continuous contractor outreach program.
BOE directed Tutor Saliba Corporation to proceed with work through the
issuance of Emergency Change Orders with Board of Public Works verbal
authorization and e-mail confirmation but before finalizing the Board Report
approval process within the 30-day requirement in the Project Delivery Manual.
The current project change order process is slowed by the time it takes to move
through several layers of authorizations and ultimately obtain approval from the
Board of Public Works. In order to keep the project moving and avoid disruption,
BOE directed Tutor-Saliba Corporation to proceed with work utilizing the existing
emergency change order process with Board of Public Works verbal authorization
and e-mail confirmation, but before finalizing the Board Report approval process
within the 30-day requirement in the Project Delivery Manual. By doing so, BOE is
risking not having sufficiently reviewed and documented scope and price justification
prior to start of work.
BOE's design driven construction change orders do not distinguish between an
error and an omission.
Currently, BOE's design driven construction change orders do not distinguish
between an error and an omission. Additionally, the design contract does not
establish a contractual ‘standard of care' against which errors and omissions should
be measured. As a result, it becomes more difficult for the City to establish and
quantify the value of an architect's failure to meet minimum standards of care, which
in turn impacts cost negotiations resulting from design errors and omissions.
SECTION II: CONSTRUCTION MANAGEMENT AGREEMENT
It is unclear if BOE obtained the most advantageous contractual rates with Vanir,
due to the limited documentation and definitive policies regarding rate
negotiation protocols.
BOE did not consider cost as one of the criteria for selection of a construction
management firm. In addition, BOE did not require a list of hourly billing rates for
key personnel and activities as part of the submission requirements in the Request
for Qualifications and did not require Vanir Construction Management, Inc. to submit
a cost proposal for their services during the selection process. Vanir Construction
Management, Inc. did submit a staff cost projection schedule with hourly rates after
they were selected, but the hourly rates were established by BOE. Additionally, it
cannot be determined if the current hourly rates takes into consideration that the City
is housing the Vanir Construction Management, Inc. staff in City rented office space.
The Vanir agreement contract terms contain limitations.
The current agreement with Vanir Construction Management, Inc. contains articles
which do not consistently define requirements, are duplicative, or may not limit
potential risk exposure for the City. All City contracts need to provide clear
definitions of terms and utilize appropriate language so that both the City and
consultant have a firm understanding of what is expected by both parties. A clearly
formulated contract also reduces the risk of disputes and promotes a successful
relationship between the City and consultant.
BOE inappropriately used Vanir's reimbursable expense allowance to quickly
procure services from DMJM.
BOE directed Vanir Construction Management, Inc. to use its reimbursable expense
allowance as a way to procure additional needed services from the architect, DMJM
Design / Roth+Sheppard Joint Venture, instead of amending the architectural
agreement. This is a questionable use of Vanir Construction Management, Inc.'s
reimbursable expense allowance.
BOE directed Vanir to begin work before a contract had been formally executed.
Vanir Construction Management, Inc. performed work prior to formal contract
execution at the direction of BOE. Issuing a ‘notice to proceed' may obligate the City
to compensate the consultant without having fully agreed to the terms or conditions
protecting either the City or Vanir Construction Management, Inc.
SECTION III: ARCHITECTURAL AND ENGINEERING AGREEMENT
BOE did not follow its own procedures when procuring and administering the
architectural and engineering contract.
BOE did not sufficiently negotiate the original DMJM Design / Roth+Sheppard Joint
Venture contract and subsequent amendments. Instead of obtaining a cost proposal
from DMJM Design / Roth+Sheppard Joint Venture, BOE proposed a cost estimate
they felt was reasonable. As a result, the City may not have obtained the best
possible price for design services.
BOE directed DMJM Design / Roth+Sheppard Joint Venture to begin work before
the contract was formally executed. This practice continued during the design and
construction phase, as DMJM Design / Roth+Sheppard Joint Venture has reportedly
completed a significant amount of work totaling $1.3 million related to Amendment
no. 3, which has not yet been executed.
BOE used DMJM Design / Roth+Sheppard Joint Venture's reimbursable expense
allowance as a contingency fund to pay for services performed by other firms. This
may not be an appropriate use of contract reimbursables, which are typically
incidental costs that are specifically related to the contract's defined scope of
services.
The contract type used by BOE may not be the best type for architectural and
engineering services.
BOE did not utilize a cost-based contract for architectural and engineering services.
Instead, a lump sum contract was executed, which may not have been the most cost
effective option when designing a unique project, such as the Police Headquarters
Facility. While BOE reportedly always uses lump sum contracts for well-defined and
routine design work, for future projects it should consider alternative contract types,
which may reduce City costs.
The DMJM agreement contract terms contain limitations.
The current agreement with DMJM Design / Roth+Sheppard Joint Venture contains
articles which do not consistently define requirements, are duplicative, or may not
limit potential risk exposure for the City. All City contracts need to provide clear
definitions of terms and utilize appropriate language so that both the City and
consultant have a firm understanding of what is expected by both parties. A clearly
formulated contract also reduces the risk of disputes and promotes a successful
relationship between the City and consultant.
REVIEW OF REPORT
Audit findings were presented and discussed with BOE on February 11, 2008, and a
draft report was subsequently provided to management. We held an exit conference
with BOE management on March 7, 2008 to discuss the contents of this report. We
considered the Bureau's comments before finalizing the report. We appreciate the
cooperation and assistance extended to us during the audit by the various departments
and offices.
|